Samra Phase IV 75 MW Add-on Combined Cycle
Middle East and North Africa
October 22, 2020K&M is providing Owner’s Engineer services to SEPCO for the construction of a 75 MW steam cycle and heat recovery steam generator (HRSG) to convert the Samra Phase IV 143 MW simple cycle gas-fired power station into a combined cycle system. K&M is assisting SEPCO with all phases of the project, from conceptual design and technical specification to selecting an EPC contractor and overseeing construction and commissioning. K&M designed and managed an international competitive bid process and selected SEPCO III as the EPC contractor for the project. K&M successfully negotiated the EPC contract with SEPCO III, and K&M is currently responsible for design review and on-site construction supervision, including quality control, schedule management, and supervision of testing and commissioning. K&M will be providing Phase 4 (warranty) services until 24 months past commissioning, March 15, 2020.