Latin America and the Caribbean
August 14, 2025The energy regulator of the Cayman Islands is planning to issue a Request for Proposal (RFP) for the development of a new thermal power plant in Grand Cayman, with an expected capacity of approximately 36.5 MW. CUC will serve as the off-taker for the power generated by the selected Independent Power Producer (IPP). K&M will support CUC by developing a draft Power Purchase Agreement (PPA) tailored to the thermal IPP project.
K&M is supporting CUC by preparing a draft Power Purchase Agreement (PPA) for the project, including identifying and recommending the allocation of responsibilities and risks between CUC and the IPP. As part of this work, K&M will adapt CUC’s existing thermal PPA to reflect project-specific requirements and will also review the Interconnection Agreement.